PipelineTop story
Kinder Morgan proposes a 470-mile natural gas pipeline that would start in Sumner County
The proposed pipeline would run 470 miles and cost $7.6 billion
- 470 miles
- from Sumner County to Monroe County, Georgia
- About 150
- miles of it in Tennessee
- $7.6 billion
- estimated cost of the full project
- About 760
- Tennessee property owners along the route
Sources: WSMV, WZTV, Thunder Radio
If you own a home in Sumner County, watch your mailbox: homeowners there are set to get a letter in the coming weeks. Kinder Morgan's Southern Natural Gas wants to build the Southeast Connector, a roughly 470-mile pipeline from Sumner County to Monroe County, Georgia. WSMV lists Wilson County on the route, but WZTV lists 10 counties that don't include it, and the route could change.
Landowners are already speaking up. WKRN says a petition among landowners along the route has been started. Marion County's Shari Lydy said the line would "probably take about four acres of my property." Kinder Morgan says the project wouldn't cost taxpayers anything and would bring millions in new tax revenue to rural economies.
- Survey offer: $500 for permission to survey a property
- Easement: generally 50 feet, negotiated with each landowner
- Jobs: about 7,000 temporary, 50 permanent
- Tennessee cost: about $1.3 billion, the company says
Kinder Morgan wants the pipeline running by the end of 2030
- Late 2026Kinder Morgan plans to request entry into FERC's pre-filing process.
- Q3 2027Kinder Morgan hopes to submit its certificate application to FERC.
- Late 2028Construction could begin.
- Late 2030Service could start, in phases.